Huntsman Petrochemical April 2000 – July 2001
Senior Mechanical Engineer, Dayton, Texas
· Responsible for support of maintenance, Back-up to Maintenance Manager
- Responsible for small capital project management
- Responsible for development and management of vibration monitoring programs
- I expanded the vibration monitoring program by 300% and gained approval to obtain a dedicated hand held analyzer for the site.
- I designed and installed a $200K hazardous powdered additive handling project. This eliminated exposure of employees to hazardous phosphorous pentaoxide dust
- Reduced spare parts inventory costs on reactor agitator seals by 90% and downtime to repair by 75% by standardizing components.
EVAL Company of America April 1994 – April 2000
Maintenance Engineer, Pasadena, Texas
- Responsible for support of mechanical maintenance of 3 Barrier resins plants (food grade ethylene vinyl alcohol). This was a sold-out specialty resin unit, of which we were 1 of 2 manufacturers in the world. We nearly drove our competitor out of business due to our ability to keep the plant running at 99% reliability and deliver product when our competitor couldn't.
- Responsible for turnaround planning and supervision. I planned and directed 2 major turnarounds, injury free. The largest turnaround, 1 month in duration, included tie-ins for a new production line that we were building. By building contingencies into the plan, it was completed 6 days early despite a 25% change in scope due to discovery work.
- Developed grass roots vibration monitoring program and performed routine analysis. My data driven recommendations on a 700 hp and 1000 hp motor avoided $2MM in lost production.
- Supervised rotating equipment check-out/commission in new unit, established spare parts inventory for 300 pieces of equipment.
- Developed grass roots maintenance & inspection policies & procedures for vessels, tanks, & piping
- Responsible for small capital project management
- Filled in for Maintenance Manager for 3 months while he was on an overseas assignment. We remained within budget and equipment on-stream time remained at 99.7%.
Quantum Chemical May 1991 to April 1994
Project Engineer, Deer Park, Texas
- Responsible for scope and estimate development, equipment specification, and supervision of construction of capital projects up to $5MM
- I managed a $300K cyanide wastewater discharge reduction project. We were under an enforcement deadline from the EPA and faced $6MM in fines. I worked with a chemist to develop a unique process design, obtained expedited approval of funds from the divisional vice president, and worked 90 hrs/week to complete this project successfully.
- I managed a $1MM air emissions reduction project in a slurry HDPE unit. We were also under an enforcement design from the EPA. A similar plant had installed a $7MM incinerator to destroy this waste. I was able to come up with a successful alternative solution for $1MM. The preliminary scope/estimate I inherited was off by over 100%. My detailed scope documents and control estimate, which eventually became a department standard, resulted in a project that was completed within 0.5% of budget.